<?xml version="1.0" encoding="UTF-8"?>
<rss version="2.0"
	xmlns:content="http://purl.org/rss/1.0/modules/content/"
	xmlns:wfw="http://wellformedweb.org/CommentAPI/"
	xmlns:dc="http://purl.org/dc/elements/1.1/"
	xmlns:atom="http://www.w3.org/2005/Atom"
	xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
	xmlns:slash="http://purl.org/rss/1.0/modules/slash/"
	>

<channel>
	<title>Nathan Jamin's Weblog &#187; Sprint Burndown</title>
	<atom:link href="http://www.njamin.org/blog/tag/sprint-burndown/feed" rel="self" type="application/rss+xml" />
	<link>http://www.njamin.org/blog</link>
	<description></description>
	<lastBuildDate>Wed, 07 Sep 2011 11:46:23 +0000</lastBuildDate>
	<language>en</language>
	<sy:updatePeriod>hourly</sy:updatePeriod>
	<sy:updateFrequency>1</sy:updateFrequency>
	<generator>http://wordpress.org/?v=3.1.4</generator>
		<item>
		<title>Sprint Burndowns in Story Points or Time?</title>
		<link>http://www.njamin.org/blog/scrum/sprint-burndowns-in-story-points-or-time-163.php</link>
		<comments>http://www.njamin.org/blog/scrum/sprint-burndowns-in-story-points-or-time-163.php#comments</comments>
		<pubDate>Thu, 23 Apr 2009 18:41:56 +0000</pubDate>
		<dc:creator>Nathan</dc:creator>
				<category><![CDATA[Scrum]]></category>
		<category><![CDATA[Ask a CSM]]></category>
		<category><![CDATA[Sprint Burndown]]></category>

		<guid isPermaLink="false">http://www.njamin.org/blog/?p=163</guid>
		<description><![CDATA[Another day, another interesting discussion at work. This time, I guess you got that, we talked about the data teams&#8217; Sprint Burndowns should be based on. Should teams have their Sprint Burndown based on Story Points or on the sum of all remaining estimated tasks in hours? To answer this question, it&#8217;s important to understand [...]

<b>Some posts that may be related:</b><li><a href='http://www.njamin.org/blog/scrum/iteration-zero-and-scrum-sprint-zero-65.php' rel='bookmark' title='Permanent Link: Iteration Zero and Scrum (Sprint Zero)'>Iteration Zero and Scrum (Sprint Zero)</a></li>
<li><a href='http://www.njamin.org/blog/scrum/challenges-of-scrum-in-distributed-teams-52.php' rel='bookmark' title='Permanent Link: Challenges of Scrum in distributed teams'>Challenges of Scrum in distributed teams</a></li>
<li><a href='http://www.njamin.org/blog/scrum/single-or-multiple-product-backlogs-143.php' rel='bookmark' title='Permanent Link: Single or Multiple Product Backlog(s)?'>Single or Multiple Product Backlog(s)?</a></li>
</ol></br>]]></description>
			<content:encoded><![CDATA[<p>Another day, another interesting discussion at work.</p>
<p>This time, I guess you got that, we talked about the data teams&#8217; Sprint Burndowns should be based on. Should teams have their Sprint Burndown based on Story Points or on the sum of all remaining estimated tasks in hours?</p>
<p>To answer this question, it&#8217;s important to understand what the goal/role of a Sprint Burndown is. The Sprint Burndown is a tool that:</p>
<p>* shows the team&#8217;s progress of a running Sprint<br />
* indicates the team&#8217;s performance during the Sprint<br />
* should show whether a team is on a good way to meet its commitment or not<br />
* shows where blocks in the development process may happen </p>
<p>Let&#8217;s do a small comparison of 2 approaches&#8230;</p>
<p><strong>1. Sprint burndown based on story points</strong></p>
<p style="text-align: left;">* doesn&#8217;t require the team to estimate tasks<br />
* might be considered as less overhead by the team<br />
* may not explicitely show bottlenecks in the development process<br />
* may have the tendency to create burndowns like this</p>
<p style="text-align: center;"><img class="size-full wp-image-168 aligncenter" title="burndown_points" src="http://www.njamin.org/blog/wp-content/uploads/2009/04/burndown_points.png" alt="burndown_points" width="255" height="162" /></p>
<p><strong>2. Sprint burndown based on time</strong></p>
<p>* requires initial tasks to be created and estimated at Sprint start<br />
* may put negative pressure on the team by introducing another level of estimations (and measuring against these estimates)<br />
* may be considered as too much overhead by the team<br />
* may show bottlenecks/blocks more explicitely than with Story Points<br />
* will have the tendency to create burndowns like this</p>
<p style="text-align: center;"><img class="size-full wp-image-171 aligncenter" title="burndown_time" src="http://www.njamin.org/blog/wp-content/uploads/2009/04/burndown_time.png" alt="burndown_time" width="286" height="170" /> </p>
<p>In summary, the purpose alone of the Burndown should already give a good idea in which direction to go. The team/company&#8217;s culture and how deep you are in your implementation of Scrum may be 2 other aspects to take into account when making that decision.</p>
<p>Now Jeff Sutherland recently wrote &#8220;The best teams I work with burn down story points. They only burn down when a story is done.&#8221; (<a href="http://jeffsutherland.com/scrum/2009/04/sprint-burndown-by-hours-or-by-story.html">Source</a>) - Are you there yet?</p>


<b>Some posts that may be related:</b><li><a href='http://www.njamin.org/blog/scrum/iteration-zero-and-scrum-sprint-zero-65.php' rel='bookmark' title='Permanent Link: Iteration Zero and Scrum (Sprint Zero)'>Iteration Zero and Scrum (Sprint Zero)</a></li>
<li><a href='http://www.njamin.org/blog/scrum/challenges-of-scrum-in-distributed-teams-52.php' rel='bookmark' title='Permanent Link: Challenges of Scrum in distributed teams'>Challenges of Scrum in distributed teams</a></li>
<li><a href='http://www.njamin.org/blog/scrum/single-or-multiple-product-backlogs-143.php' rel='bookmark' title='Permanent Link: Single or Multiple Product Backlog(s)?'>Single or Multiple Product Backlog(s)?</a></li>