Sprint Burndowns in Story Points or Time?
Scrum | (2)
Another day, another interesting discussion at work.
This time, I guess you got that, we talked about the data teams' Sprint Burndowns should be based on. Should teams have their Sprint Burndown based on Story Points or on the sum of all remaining estimated tasks in hours?
To answer this question, it's important to understand what the goal/role of a Sprint Burndown is. The Sprint Burndown is a tool that:
* shows the team's progress of a running Sprint
* indicates the team's performance during the Sprint
* should show whether a team is on a good way to meet its commitment or not
* shows ...